| Process Group | PMBOK | Knowledge Area Process | Why? (inputs) | How? (tools and techniques) | What? (outputs) |
| ¡¡ | ¡¡ | ¡¡ | ¡¡ | ¡¡ | ¡¡ |
| Planning | 6.1 | Activity Definition |
|
|
|
| Planning | 6.2 | Activity Sequencing |
|
|
|
| Planning | 6.3 | Activity Duration Estimating |
|
|
|
| Planning | 6.4 | Schedule Development |
|
|
|
| Controlling | 6.5 | Schedule Control |
|
|
|
1. Expected Mean Value = (optimistic + (4 * most likely) + pessimistic) /6
2 Resource Leveling = use resources effectively, however will normally change critical path and will lengthen the project¡¯s duration.
3. Standard Deviation = (Pessimistic Estimate ¨C Optimistic Estimate) / 6
4. Cumulative Cost Curve = Best tool for tracking project cost
5. Slack = Early Start ¨C Late Start
6. Early Finish = Early Start + duration
7. Late Start = Late Finish ¨C Duration
8. Gantt Chart = Used to track actual vs. planned for schedule control.
9. Pert = Best for what if, measures future consequences of activities.
10. Fast Tracking = used in order to speed up those task. Doing tasks in parallel with each other.
11. Crashing the Schedule Rules = Only crash those on the critical path and begin crashing only those
tasks which cost the least amount first.
12. AOA = Event Oriented
13. AON = Activity Oriented